The bill directs the PSC to conduct a study on relieving transmission
constraints in other states that adversely affect the reliability of electric service
provided to customers in this state. The PSC must submit a report on the study to
the legislature that describes the transmission constraints, the efforts undertaken

to relieve the constraints and any recommendations, in the form of proposed
legislation or action by the PSC or the governor, for relieving the constraints.
Strategic energy assessment and certificates of public convenience and
necessity
The bill eliminates the requirement for certain public utilities and cooperative
associations to submit advance plans for approval by the PSC and requires instead
that the PSC prepare a strategic energy assessment. In addition, the bill makes
changes to the requirements pertaining to the certificates of public convenience and
necessity that a person must obtain in order to construct certain electric generating
facilities, transmission lines and other projects.
Strategic energy assessment
Under current law, certain public utilities and cooperative associations are
required to submit biennial advance plans to the PSC that include certain
information about their plans to construct the following: 1) "large electric generating
facilities", which are defined as facilities with a capacity of between 12,000 and
300,000 kilowatts; 2) "bulk electric generating facilities", which are defined as
facilities with a capacity of 300,000 kilowatts or more; and 3) "high-voltage
transmission lines", which are defined as lines that are longer than one mile and that
operate at 100 kilovolts or more. After holding a hearing on a plan, the PSC may
approve a plan if the PSC finds that that plan will provide a reasonably adequate
supply of electrical energy to meet the needs of the public and that the plan satisfies
certain other criteria. A public utility or cooperative association must also submit
an advance plan to the lower Wisconsin state riverway board (board) if it intends to
construct, modify or relocate a high-voltage transmission line in the lower Wisconsin
riverway (riverway). The board must approve the plan if it determines that the
high-voltage transmission line will not impair, to the extent practicable, the scenic
beauty or natural value of the riverway.
This bill eliminates the requirements pertaining to advance plans and requires
instead that the PSC prepare an annual strategic energy assessment that evaluates
the adequacy and reliability of the state's current and future energy supply. In
addition, the bill requires a person to obtain a permit from the board in order to
construct, modify or relocate a high-voltage transmission line in the riverway. The
board may not issue the permit unless it makes the same determination as under
current law.
The strategic energy assessment must identify and describe facilities that
generate over 200,000 kilowatts on which public utilities, cooperative associations
and certain other persons plan to begin construction within 3 years. The strategic
energy assessment must also include information about high-voltage transmission
lines on which a public utility or cooperative association plans to begin construction
in the next 18 months. In addition, the strategic energy assessment must describe
all of the following: 1) any plans for assuring that there is an adequate ability to
transfer electric power into the state and the area served by MAIN; 2) the projected
demand for electric power; 3) activities to discourage inefficient and excessive power
use; 4) existing and planned generating facilities that use renewable energy sources;
5) the extent to which the regional bulk-power market is contributing to the

adequacy and reliability of the state's electrical supply; 6) the extent to which
effective competition is contributing to a reliable, low-cost and environmentally
sound source of electricity; and 7) whether sufficient electric capacity and energy is
available at a reasonable price. The PSC must promulgate rules that require public
utilities and cooperative associations to report information that is necessary for the
PSC to prepare the strategic energy assessment.
The PSC is required to issue a draft version of the strategic energy assessment
no later than July 1 of each year. Any state agency, county, municipality, town or
person may submit comments on the draft. The PSC must hold a public hearing on
the strategic energy assessment and, at least 30 days before the hearing, the PSC
must make available to the public an environmental assessment that it prepares on
the strategic energy assessment. Within 90 days after the hearing, the PSC must
issue a final version of the draft.
Certificates of public convenience and necessity
Under current law, a person may not begin constructing a large or bulk electric
generating facility or high-voltage transmission line without obtaining a certificate
of public convenience and necessity (certificate) from the PSC. A person that is not
a public utility or cooperative association is exempt from this requirement if the
person reasonably anticipates that the person will consume no less than 70% of the
aggregate kilowatt hours output from electric generating facilities in manufacturing
processes at the site where the facilities are located. Before filing an application for
a certificate for a large or bulk electric generating facility, a person must provide an
engineering plan to the department of natural resources (DNR), which must provide
the person with a list of DNR permits and approvals that, based on the engineering
plan, appear to be required for the facility. In consultation with the PSC, DNR may
specify whether any permits or approvals must be obtained before the PSC may issue
the certificate.
Also under current law, the PSC must take final action on an application for a
certificate, and DNR must take final action on an application for the permits and
approvals, within specified deadlines that depend on whether the application
concerns a large or bulk electric generating facility or a high-voltage transmission
line. After holding a public hearing on an application for a certificate, the PSC must
issue the certificate if it makes certain determinations, including the following: 1) the
proposed facility or line is in substantial compliance with the most recent advance
plan; 2) the proposed facility or line is necessary to satisfy the reasonable needs of
the public; 3) the design and location are in the public interest; 4) the proposed
facility or line will not have an undue adverse impact on environmental values; and
5) the proposed facility or line will not unreasonably interfere with orderly land use
and development plans. However, the PSC may not issue a certificate until DNR
issues the specified permits and approvals.
This bill changes the types of facilities that are subject to the above
requirements and changes the procedure for issuing a certificate by the PSC and the
permits and approval by DNR. The bill requires a person to obtain a certificate from
the PSC before beginning construction of any of the following: 1) "large electric
generating facilities", which the bill defines as facilities with a capacity of 50,000

kilowatts or more; and 2) "high-voltage transmission lines", which the bill defines
as lines that are longer than 5 miles but that operate at the same voltage as under
current law.
The bill requires a person to file an application for a certificate within 6 months
before beginning construction. The PSC must notify the applicant about whether an
application is complete within 30 days after filing and a person may refile an
incomplete application. If the PSC does not determine whether an application is
complete within the 30-day deadline, the application is considered to be complete.
At the same time that a person applies for a certificate, the person must provide DNR
with an engineering plan and, within 30 days after receiving the plan, DNR must
provide the person with a list of permits and approvals that appear to be applicable.
Within 20 days after DNR provides the list, the person must apply for the permits
and approvals. DNR is subject to a similar 30-day deadline in which DNR must
notify an applicant about whether an application is complete. DNR must complete
action on the permits and approvals within 90 days after an application is
determined or considered to be complete.
Within 180 days after an application for a certificate is determined or
considered to be complete, the PSC must take final action on the application, unless
the circuit court for Dane County grants an extension. After holding a public
hearing, the PSC may issue a certificate only if it makes the same determinations
under current law described above, except for the first determination regarding
compliance with an advance plan. In addition, the PSC does not have to make the
2nd determination regarding need if a large electric generating facility is a
"wholesale merchant plant", which the bill defines as electric generating facilities
that do not provide service to any retail customer and that are owned by a person who
is not a public utility, an affiliate of a public utility, or a cooperative association. Also,
the PSC must determine that the proposed large electric generating facility or
high-voltage transmission line will not have a material adverse impact on
competition in the relevant wholesale electric service market. Such a determination
is not required under current law. Finally, the PSC may not issue a certificate until
the DNR has issued the permits and approvals identified in the list provided by the
DNR.
The bill also changes the exemption from the requirement to obtain a
certificate. Under the bill, a person that is not a public utility or cooperative
association may qualify for the exemption only if the person is also not a public utility
affiliate or otherwise affiliated with a public utility.
Public utility construction projects
Under current law, the PSC may require that a public utility obtain a certificate
of public convenience and necessity before it begins certain construction projects.
Under this bill, a public utility that provides electric service is exempt from this
requirement if the project is not the construction of a nuclear power plant and the
cost of the project is less than an amount based on the public utility's annual gross
operating revenues. If a public utility's annual gross operating revenues are less
$5,000,000, the exemption applies to projects that cost less than $100,000. If such
revenues are between $5,000,000 and $250,000,000, the exemption applies to

projects that cost less than 2% of the revenues. If such revenues are more than
$250,000,000, the exemption applies to projects that cost less than $5,000,000.
Out-of-state electric power sales
The bill requires the PSC, in setting rates, to reduce the revenue requirement
of a public utility by an amount that reflects the fixed capital costs of electric
generating facilities within the state that are incurred to make sales to customers
outside the state whom the public utility does not have a duty to serve. The bill also
prohibits a public utility from making such a sale if the sale interferes with the public
utility's ability to provide cost-effective, reliable electric service to customers in this
state that the public utility has a duty to serve.
Large electric generating facility standards
The bill requires the PSC to promulgate rules establishing standards for the
inspection, maintenance, operation and repair of large electric generating facilities
that are owned by, or provide service to, public utilities. "Large electric generating
facilities" are defined as facilities with a capacity of 50,000 kilowatts or more. The
PSC must also promulgate rules establishing penalties for violating the standards.
Other
For further information see the state and local fiscal estimate, which will be
printed as an appendix to this bill.
The people of the state of Wisconsin, represented in senate and assembly, do
enact as follows:
AB748, s. 1 1Section 1. 30.025 (1) of the statutes is amended to read:
AB748,7,102 30.025 (1) Any electric utility, as defined in s. 196.491 (1) (d), proposing to
3construct a facility, as defined in s. 196.491 (1) (e), which facility is to be located
4adjacent to a waterway in such a manner as to require one or more permits to be
5issued under this chapter and ch. 31 may, in lieu of separate application for permits
6under those chapters, submit an engineering plan together with any additional
7information required by the department. Such plan shall be filed with the
8department within 20 days after an application for a certificate of public convenience
9and necessity is filed with the public service commission under s. 196.491 (3). The
10department may require supplemental information to be furnished thereafter.
AB748, s. 2 11Section 2. 30.025 (4) of the statutes is amended to read:
AB748,8,4
130.025 (4) The permit may be issued upon stated conditions deemed necessary
2to assure compliance with the criteria designated under sub. (3). The department
3shall grant or deny the application within the time limit applicable under s. 196.491
4(3) (f) (a) 3. b.
AB748, s. 3 5Section 3. 30.44 (3m) (title) of the statutes is amended to read:
AB748,8,66 30.44 (3m) (title) Utility facilities ; high-voltage transmission lines.
AB748, s. 4 7Section 4. 30.44 (3m) (a) of the statutes is amended to read:
AB748,8,108 30.44 (3m) (a) A person shall apply to and receive a permit from the board
9before constructing, modifying or relocating a utility facility or high-voltage
10transmission line
that is in the riverway.
AB748, s. 5 11Section 5. 30.44 (3m) (b) of the statutes is amended to read:
AB748,8,1512 30.44 (3m) (b) A person may not be issued a permit for an activity in par. (a)
13unless the performance standard in par. (c) is met and, for a high-voltage
14transmission line, the board finds that the activity will not impair, to the extent
15practicable, the scenic beauty or natural value of the riverway
.
AB748, s. 6 16Section 6. 30.44 (3m) (d) of the statutes is amended to read:
AB748,8,2017 30.44 (3m) (d) The use of an aboveground utility facility shall not be a basis for
18the board to determine that all reasonable efforts will not be taken to minimize the
19visual impact. The board may not require a high-voltage transmission line to be
20placed underground in order to make the finding specified in par. (b).
AB748, s. 7 21Section 7. 30.45 (1r) of the statutes is amended to read:
AB748,8,2422 30.45 (1r) No person may construct, modify or relocate a high-voltage
23transmission line unless it has been approved under s. 30.44 (3m) or 196.491 (3) (d)
243m. or 196.492.
AB748, s. 8 25Section 8. 32.03 (5) (a) of the statutes is amended to read:
AB748,9,6
132.03 (5) (a) If an electric utility is required to obtain a certificate of public
2convenience and necessity from the public service commission under s. 196.491 (3),
3no right to acquire real estate or personal property appurtenant thereto or interest
4therein for such project by condemnation shall accrue or exist under s. 32.02 or
532.075 (2) until such a certificate of public convenience and necessity has been
6issued.
AB748, s. 9 7Section 9. 32.03 (5) (b) 1. of the statutes is amended to read:
AB748,9,88 32.03 (5) (b) 1. Such a limited interest does not run for more than 3 years; and
AB748, s. 10 9Section 10. 32.03 (5) (b) 2. of the statutes is amended to read:
AB748,9,1210 32.03 (5) (b) 2. Activities associated with such tests or studies will be conducted
11at reasonable hours with minimal disturbance, and the property will be reasonably
12restored to its former state, upon completion of such tests or studies ; and.
AB748, s. 11 13Section 11. 32.03 (5) (b) 3. of the statutes is repealed.
AB748, s. 12 14Section 12. 32.06 (7) of the statutes is amended to read:
AB748,9,2515 32.06 (7) Petition for condemnation proceedings. If the jurisdictional offer
16is not accepted within the periods limited in sub. (6) or the owner fails to consummate
17an acceptance as provided in sub. (6), the condemnor may present a verified petition
18to the circuit court for the county in which the property to be taken is located, for
19proceedings to determine the necessity of taking, where such determination is
20required, and the amount of just compensation. The petition shall state that the
21jurisdictional offer required by sub. (3) has been made and rejected; that it is the
22intention of the condemnor in good faith to use the property or right therein for the
23specified purpose. It shall name the parties having an interest of record in the
24property as near as may be and shall name the parties who are minors or persons of
25unsound mind or unknown. The petition may not disclose the amount of the

1jurisdictional offer, and if it does so it is a nullity. The petition shall be filed with the
2clerk of the court. Notice of the petition shall be given as provided in s. 32.05 (4) to
3all persons having an interest of record in the property, including the special
4guardian appointed for minors or incompetent persons. A lis pendens shall be filed
5on the date of filing the petition. The date of filing the lis pendens is the "date of
6evaluation" of the property for the purpose of fixing just compensation, except that
7if the property is to be used in connection with the construction of a facility, as defined
8under s. 196.491 (1), the "date of evaluation" is the date that the first advance plan
9identifying the property as a site or route under s. 196.491 (2) (a) 3. is filed with the
10public service commission, or the date which
is 2 years prior to the date on which the
11certificate of public convenience and necessity is issued for the facility, whichever is
12earlier
. The hearing on the petition may not be earlier than 20 days after the date
13of its filing unless the petitioner acquired possession of the land under s. 32.12 (1)
14in which event this hearing is not necessary. If the petitioner is entitled to condemn
15the property or any portion of it, the judge immediately shall assign the matter to the
16chairperson of the county condemnation commissioners for hearing under s. 32.08.
17An order by the judge determining that the petitioner does not have the right to
18condemn or refusing to assign the matter to the chairperson of the county
19condemnation commissioners may be appealed directly to the court of appeals.
AB748, s. 13 20Section 13. 32.07 (1) of the statutes is amended to read:
AB748,10,2321 32.07 (1) A certificate of public convenience and necessity issued under s.
22196.491 (3) shall constitute the determination of the necessity of the taking for any
23lands or interests described in the certificate.
AB748, s. 14 24Section 14. 32.07 (1m) of the statutes is repealed.
AB748, s. 15 25Section 15. 32.075 (3) (a) 2. of the statutes is amended to read:
AB748,11,6
132.075 (3) (a) 2. The public service commission revokes a certificate of public
2convenience and necessity required under s. 196.491 (3) (a) 1. or finds that a state
3or federal agency has denied or revoked any license, permit, certificate or other
4requirement on which completion of the public utility's project for which the land was
5condemned is contingent or that the public utility has for any other reason
6abandoned a project for which the condemned property was acquired.
AB748, s. 16 7Section 16. 32.09 (2m) of the statutes is amended to read:
AB748,11,138 32.09 (2m) In determining just compensation for property sought to be
9condemned in connection with the construction of facilities, as defined under s.
10196.491 (1) (e), any increase in the market value of such property occurring after the
11date of evaluation but before the date upon which the lis pendens is filed under s.
1232.06 (7) shall be considered and allowed to the extent it is caused by factors other
13than the planned facility.
AB748, s. 17 14Section 17. 66.073 (10) (a) of the statutes is renumbered 66.073 (10).
AB748, s. 18 15Section 18. 66.073 (10) (b) of the statutes is repealed.
AB748, s. 19 16Section 19. 86.16 (1) of the statutes is amended to read:
AB748,11,2417 86.16 (1) Any person, firm or corporation, including any foreign corporation
18authorized to transact business in this state may, subject to ss. 30.44 (3m), 30.45, and
19196.491 (3) (d) 3m. and 196.492, with the written consent of the department with
20respect to state trunk highways, and with the written consent of local authorities
21with respect to highways under their jurisdiction, including connecting highways,
22construct and operate telegraph, telephone or electric lines, or pipes or pipelines for
23the purpose of transmitting messages, water, heat, light or power along, across or
24within the limits of the highway.
AB748, s. 20 25Section 20. 182.017 (1) of the statutes is amended to read:
AB748,12,14
1182.017 (1) Right-of-way for. Any domestic corporation organized to furnish
2telegraph or telecommunications service or transmit heat, power or electric current
3to the public or for public purposes, and any cooperative association organized under
4ch. 185 to furnish telegraph or telecommunications service or transmit heat, power
5or electric current to its members, may, subject to ss. 30.44 (3m), 30.45, 86.16, and
6196.491 (3) (d) 3m. and 196.492 and to reasonable regulations made by any city,
7village or town through which its transmission lines or systems may pass, construct
8and maintain such lines or systems with all necessary appurtenances in, across or
9beneath any public highway or bridge or any stream or body of water, or upon any
10lands of any owner consenting thereto, and for such purpose may acquire lands or
11the necessary easements; and may connect and operate its lines or system with other
12lines or systems devoted to like business, within or without this state, and charge
13reasonable rates for the transmission and delivery of messages or the furnishing of
14heat, power or electric light.
AB748, s. 21 15Section 21. 196.01 (5) of the statutes is renumbered 196.01 (5) (a) (intro.) and
16amended to read:
AB748,12,1717 196.01 (5) (a) (intro.) "Public utility" means every each of the following:
AB748,12,25 181. Every corporation, company, individual, association, their lessees, trustees
19or receivers appointed by any court, and every sanitary district, town, village or city
20that may own, operate, manage or control any toll bridge or all or any part of a plant
21or equipment, within the state, for the production, transmission, delivery or
22furnishing of heat, light, water or power either directly or indirectly to or for the
23public. "Public utility" does not include a cooperative association organized under
24ch. 185 for the purpose of producing or furnishing heat, light, power or water to its
25members only. "Public utility" includes any
AB748,13,4
12. A person engaged in the transmission or delivery of natural gas for
2compensation within this state by means of pipes or mains and any person, except
3a governmental unit, who furnishes services by means of a sewerage system either
4directly or indirectly to or for the public. "Public utility" includes a
AB748,13,5 53. A telecommunications utility. "Public utility" does not include a
AB748,13,9 6(b) 1. A holding company, as defined in s. 196.795 (1) (h), unless the holding
7company furnishes, directly to the public, telecommunications or sewer service, heat,
8light, water or power or, by means of pipes or mains, natural gas. "Public utility" does
9not include any
AB748,13,13 102. A company, as defined in s. 196.795 (1) (f), which owns, operates, manages
11or controls a telecommunications utility unless the company furnishes, directly to
12the public, telecommunications or sewer service, heat, light, water or power or, by
13means of pipes or mains, natural gas. "Public utility" does not include a
AB748,13,14 143. A cellular mobile radio telecommunications utility.
AB748, s. 22 15Section 22. 196.01 (5) (a) 4. and (b) (intro.) and 4. of the statutes are created
16to read:
AB748,13,1817 196.01 (5) (a) 4. The independent system operator, as defined in s. 196.485 (1)
18(a).
AB748,13,1919 (b) (intro.) "Public utility" does not include any of the following:
AB748,13,2120 4. A cooperative association organized under ch. 185 for the purpose of
21producing or furnishing heat, light, power or water to its members only.
AB748, s. 23 22Section 23. 196.025 of the statutes is amended to read:
AB748,14,3 23196.025 Duties of the commission. To the extent cost-effective, technically
24feasible and environmentally sound, the commission shall implement the priorities
25under s. 1.12 (4) in making all energy-related decisions and orders, including

1advance plan, rate setting and rule-making orders, and in preparing strategic
2energy assessments under s. 196.491 (2) (a) and approving certificates of public
3convenience and necessity under s. 196.491 (3)
.
AB748, s. 24 4Section 24. 196.03 (5m) of the statutes is created to read:
AB748,14,95 196.03 (5m) In setting rates for retail electric service, the commission shall
6reduce the revenue requirement of a public utility by an amount that reflects, as
7determined by the commission, the fixed capital costs of generating facilities within
8the state that are incurred to make any sale to a customer outside this state that the
9public utility does not have a duty to serve.
AB748, s. 25 10Section 25. 196.03 (7) of the statutes is created to read:
AB748,14,1611 196.03 (7) (a) If the commission determines after notice and hearing that an
12adequate supply of retail electric service will not be available to public utility
13customers at reasonable rates, the commission may order a public utility that has
14a duty to serve retail electric customers to take measures that ensure that an
15adequate supply of retail electric service will be available to such customers at
16reasonable rates, including doing any of the following:
AB748,14,2017 1. Constructing or contracting for the construction of, on an individual basis
18or jointly with other public utilities, electric generation or transmission facilities. An
19order under this subdivision requiring a public utility to enter into contracts shall
20require the public utility to solicit competitive bids for the contracts.
AB748,14,2121 2. Purchasing electric capacity and energy.
AB748,14,2222 3. Participating in regional associations, power pools and networks.
AB748,14,2423 4. Taking any other measure that the commission determines is necessary to
24ensure an adequate supply of retail electric service at reasonable rates.
AB748,15,2
1(b) The commission shall establish mechanisms that it determines to be just
2and reasonable for the recovery of the costs of the measures specified in par. (a).
AB748, s. 26 3Section 26. 196.375 (title) of the statutes is amended to read:
AB748,15,5 4196.375 (title) Adequate service; reasonable rates; reliable retail
5electric service
.
AB748, s. 27 6Section 27. 196.375 of the statutes is renumbered 196.375 (1) and amended
7to read:
AB748,15,168 196.375 (1) Upon complaint by any party affected, setting forth that any
9grantee of a permit to develop hydraulic power and generate hydroelectric energy for
10sale or service to the public is not furnishing consumers of this state with adequate
11service at a reasonable rate as a result of sales of the energy outside of the state, the
12commission may declare any or all contracts entered into by the grantee for the sales
13null and void insofar as the contracts interfere with the service or rate. The
14commission may not make a declaration under this section subsection except after
15a hearing and investigation and a recorded finding that convenience and necessity
16require the sale of a specified part or all such energy within this state.
AB748, s. 28 17Section 28. 196.375 (2) of the statutes is created to read:
Loading...
Loading...